Higher Flows Being Reduced on Portion of Pit River

Pacific Gas and Electric Company (PG&E) has begun reducing higher flows on a portion of the Pit River, and will reduce again to seasonal normal flows in late October.

Flows had been above 2,000 cubic feet per second (cfs) in the Pit 5 Reach since February while the Pit 5 Powerhouse near Big Bend has been off line. The powerhouse was unable to operate after winter storms deposited gravel and sand in front of the powerhouse’s tailrace, where water exits the powerhouse and returns to the river.

The Pit 5 Reach is the 9.3-mile portion of the Pit River between the Pit 5 Reservoir and the Pit 5 Powerhouse.

Flows in the Pit 5 Reach were reduced from above 2,000 cfs to about 1,300 cfs after one of the four generating units at the powerhouse resumed operation on October 5.  PG&E continues to remove sediment from in front of the tailrace so it can resume operation to the other three generating units at the Pit 5 Powerhouse.

In late October, PG&E expects to resume operations on a second generating unit at the powerhouse, at which point water will stop spilling from the Pit 5 Dam and flows in the Pit 5 Reach will return to about the season normal of about 350 cfs, depending on rainy conditions.

The other two generating units are expected to return to service in late fall.

The Pit 5 Powerhouse Road and the J.B. Black Powerhouse Recreation Area’s boat put-in, take-out remain closed to the public while the Pit 5 Powerhouse Road is repaired. The road was damaged in last winter’s storms should reopen in late fall.

Advertisement

Leave a comment

Filed under Big Bend, PG&E, Pit River

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s